Plant Orders

Updated over a month ago

The basic steps in processing plant orders are as follows:

  1. Enter the order.

  2. Commit the order.

  3. Print the order.

  4. If the order uses GRNs, enter the goods received (plant advice) note. This generates a "plant on site" record.

  5. If the order uses plant allocations, allocate and confirm the plant sheets. This generates an accrual.

  6. If the order does not use plant allocations, you only need to off hire the plant items.

  7. Enter invoices.

  8. Match invoices.

Plant orders configuration

Charges for plant hire can be calculated using any of four different methods. Various parameters need to be set:

  • Hourly

    • HRSUNITS - Units that represent hours

    • HRSDAY - The number of hours in a day

    • INCOTHHR - Whether to include 'other' hourly rates from the hire style

  • Daily/weekly

    • DLYUNITS - Units that represent weeks

    • DAYUNITS - Units that represent days

    • INCOTHWK - Whether to include 'other' weekly rates from the hire style

  • Monthly

    • MLYUNITS - Units that represent months

  • Lump sum

    • LUMPSUM - Units that represent lump sum payments

    • GLOBLUMP - Whether lump sum units apply to all commodities

You need to set up plant hire styles to cover the different charging patterns for plant, using plant hire Styles. Set the default hire style for each item using plant.

Depending on the hire style, hire charges can apply on holidays or not. Set up standard holidays using Holiday Calendar (hired-in plant), and specific holidays that apply to individual contracts or customers using Customer/Contract Free Days.