Budget and Forecast Separate Regular Time, Overtime, and Double Time Hours

Updated over a month ago

Overview

This functionality allows you to budget and forecast labour hours broken down by regular time, overtime, and double time, rather than using a single blended rate.

Configuration

  1. Go to System > Parameters.

  2. Locate the JC/BUDHRTYPE parameter.

    This parameter cannot be configured per contract. JC/BUDHRTYPE is a system-wide parameter.

  3. Select which hour types you want to use (multi-select):

    • Regular

    • Overtime

    • Double Time

Initial Data Migration

  1. Navigate to Administration > Contract Status > Populate Hour Specific Budgets.

  2. Run the utility for your contracts. This moves existing "total hours" into "regular hours".

Exclude service management contracts when running this utility.

Budget Input Workbench

  • Hours now appear as separate rows for each hour type.

  • Each row can have different rates.

  • Enter hours to complete for each type.

  • Coins ERP+ calculates total cost based on individual rates.

    • You must ensure Regular + Overtime + Double Time hours = Total hours.

    • Warnings will appear if hours do not add up correctly.

Input Budget by Period

  • Hours are shown in separate columns (Regular, Overtime, Double Time).

  • Costs are shown separately for each type.

  • No rates are displayed (just hours and costs).

Job Summary Enquiry

  • Column set options allow you to see:

    • Total hours plus breakdown by type.

    • Rates for each hour type.

Cost Forecast View

  • Hour types appear as separate rows (like the Budget Input Workbench).

  • You can specify different forecast items for regular, overtime, and double time.