You can apportion the non-sellable part of a VAP budget over the sellable plots on a development.
For example, this allows the cost of an apartment shell structure or garage block to be spread over the sellable plots associated with it.
To specify the ratios for apportionment:
In development Details, click the More > tab, then click the Apportionment tab.
Click
to add a new record.
Enter a source plot - the non-sellable plot.
Enter a target plot - the sellable plot to spread the costs over. You can enter several records for the same source plot.
Select a split method:
Manual. This allows you to specify a figure that is used as the ratio for apportioning the costs. For example, if the non-sellable plot is a garage block with four garages, of which two belong to plot 001, and the other two belong to plots 002 and 003, you could enter three records as follows:
Source Plot | Source House Type | Target Plot | Target House Type | Split Method | Split |
901 | Garage Block A | 001 | Stuart | Manual | 2.0000 |
901 | Garage Block A | 002 | Tudor | Manual | 1.0000 |
901 | Garage Block A | 003 | Tudor | Manual | 1.0000 |
6. Notional Area, floor area, Density, Frontage. These allow you to use the value from a field on the plot record as the ratio for apportioning costs. For example, if the non-sellable plot is the structure of a block of apartments, you might choose to apportion the costs on the basis of the floor area of each of the apartments:
Source Plot | Source House Type | Target Plot | Target House Type | Split Method | Split |
910 | Apartment Shell | 051 | Carmona | floor area | 1,250.0000 |
910 | Apartment Shell | 052 | Merida | floor area | 1,500.0000 |
910 | Apartment Shell | 053 | Vitoria | floor area | 1,000.0000 |
7. Click.
8. Do this for each plot to which you want to allocate costs.
To apportion the budgets:
Go to Apportion Budget.
Specify the development for which you want to apportion the costs, the source budget (that has the costs applied to non-sellable plots), and the target budget to receive the apportioned costs.
You must set up the target budget in advance.
Select the output options for the report and click
.
Coins ERP+ runs a background process to write the apportioned costs into the target budget.