The Scheduler allows you to schedule Customer Care tasks by dragging and dropping them onto a calendar-style view of operatives and time slots.

Written by Sunil Pandya

Scheduler Screen

To Schedule

The To Schedule panel on the left lists the unscheduled tasks. These are the same records as shown on the ‘Unscheduled’ tasks tab in the Customer Care workbench. You can filter the tasks, for example to show only tasks for selected developments.

A link on the development/plot text in the task cell takes you to the task summary page in the Customer Care workbench.

For each unscheduled task, the following details of the task are shown:

  • Task Reference

  • Task Reason

  • Development Number

  • Development Name

  • Plot

  • First part of instructions

  • Duration

  • SLA Date

The SLA Date shown is the earliest SLA date based on the issues assigned to the task. This is coloured red if the date is before today, amber if today and green if in future.

The following icons may be shown on the tasks:

Icon

Meaning

The task has been allocated to a single operative.

The task has been allocated to more than one operative.

A task scheduling note has been entered. Click this to update the notes; this opens a browse of scheduling notes for the task.

Special conditions exist for the plot.

A tooltip shows further details of the task, such as the address, task instructions, and issues associated with the task.

Closed

A similar tooltip is shown when you move the mouse pointer over a scheduled task.

Operatives

The ‘Operatives’ column shows the Customer Care operatives. For each operative this shows their name and job title. A mobile phone icon is shown in the top right if the operative is a mCare user.

The total hours and number of tasks allocated for the day or days in the current view are shown at the bottom of each operative row. This is recalculated automatically as the calendar and tasks are updated.

Operatives Column

A tooltip shows additional details such as the operative‘s telephone numbers.

You can filter the list of operatives.

Scheduled Tasks

The main part of the schedule screen shows the tasks that have already been scheduled, as a calendar view. The calendar also shows other Activity Workbench entries, such as holidays. Entries not related to Customer Care are not updateable.

You can change the timescale for the tasks view by clicking the buttons at the top of the calendar:

  • Single day view shows details of the tasks for a specific day for each operative. This is broken down into one-hour time slots, running from midnight to midnight. By default the leftmost time slot is the time specified in the new HS parameter SCHSTIME.

  • Multi-day views (five day view, seven day view or 14 day view) show details of the tasks for multiple days for each operative.

The Work Week button allows you to exclude weekends from the view.

Day View Buttons

Navigation buttons allow you to move backwards or forwards through the days or weeks, and the date picker button allows you to choose a specific date to show.

Date Navigation Buttons

The Scheduler remembers the view you select; next time you run the scheduler it will show the same view.

Refresh

The refresh button reloads the list of unscheduled tasks, and the current information shown in the schedule window.

Refresh Button


Parameters

HS/SHC2USE

Use drag and drop task scheduler? (COINS ERP+)

Use the drag and drop task scheduler.

Only one of SCH2USE and SCHUSE should be set to Yes.

HS/SHC2KCOS

COINS companies to include in the task scheduler (COINS ERP+)

COINS companies to include on the drag and drop task scheduler.

If left blank the task scheduler will continue to only work for tasks in the current company.

HS/SHC2KTIM

Keep original time when rescheduling tasks for the same operative

If set to Y then when a task is moved from one day to another for the same operative in the Task Scheduler, if possible the same time will be kept and just the date of the task will change.

If the time slot is unavailable on the new date, the time will be rescheduled in the same way that it is currently.

HS/SHC2KTSD

Keep original time when rescheduling tasks within the same day

If set to Y then when a task is moved from one operative to another for the same date, then where possible the same time will be kept and just the task's operative will be changed.

HS/SHC2STDY

Start day for task scheduler screen

If set, then the Task Scheduler view will always show the current week beginning on the day the parameter has been set to.

The default if the parameter is not set is for the view to begin today.

HS/SHC2STIM

Default task scheduler start time for day view (COINS ERP+)

The default start time for the day view in the drag and drop task scheduler. When selecting the day view the first time shown will be this time.

The following parameters let you configure which fields are shown on the scheduler screen:

HS/SHC2TFD1

Scheduler day view task fields for first row

User-defined text for the first row of a day-based Scheduler task tile.

You can use include any database field from the following tables by placing the field in curly braces:

  • hs_task (task table)

  • hs_complaint (call table)

  • vp_wbsdef (plot table)

  • vp_site (development table)

  • jc_job (contract table)

In addition you can add a pipe to specify the number of characters to show. For example: {job_num} {vsi_name|15} would show all of the contract number (job_num) and the first 15 characters of the development name (vsi_name).

HS/SHC2TFD2

Scheduler day view task fields for second row

User-defined text for the second row of a day-based Scheduler task tile.

HS/SHC2TFW1

Scheduler weekly view task fields for first row

User-defined text for the first row of a weekly-based Scheduler task tile.

HS/SHC2TFW2

Scheduler weekly view task fields for second row

User-defined text for the second row of a weekly-based Scheduler task tile.

See also:

HS/SCHNOTE

Event code for schedule notes

The Customer Care Scheduling screen allows you to enter notes when scheduling operatives. These will appear as an event against the call history. If you want to enable this you should set this parameter to the user event code you want to associate with the created event.

HS/TASKAPTT

Activity W/B appt type for internal tasks

A valid activity workbench action type.

When a new customer care task is added for an internal member of staff, a corresponding appointment with this action type is created on their Activity Workbench (Old).

HS/SCHUSE

Use customer care scheduling?

Set to Y if you wish to use the "old" Customer Care scheduling functionality.

Only one of SCH2USE and SCHUSE should be set to Yes.


Sales Staff - Working Day

New fields on the Sales Staff record allow you to record the start and end time of the staff member’s working day.

Open

In the day view, non-working hours will be greyed out (although tasks can still be scheduled in these times), and the Start Time is used when making a task the first task of the day.


Filtering

You can filter both the unscheduled tasks and the operatives.

  1. Click the filter button above the To Schedule column.

  2. In the Filter, fill in the details of how you want to filter.

    Filter

    This includes the following options:

    • Development Number (with a lookup on developments)

    • Development Name (with a lookup on developments)

    • Plots (no lookup)

    • Operatives (with a lookup on staff).

    • Staff - This includes options to show operatives only, other staff, TBA staff or all staff.

    • Unscheduled Tasks SLA - This includes the following options: All, Outside SLA, Out of SLA in 3 days, Out of SLA in 7 days.

    In the Development Number, Development Name, Plot and Operatives fields, you can use standard Coins ERP+ can-do lists.

  3. Click the Filter On button, then click OK.

The filter button shows a yellow icon to indicate that the filter is active.


Scheduling a Task

To schedule an unscheduled task, drag it from the To Schedule list and drop it onto the calendar for a specific operative and time.

The duration of the task is shown at the bottom right of the scheduled task. If an unscheduled task has duration specified, when the task is dropped onto the calendar a default duration will be assumed. This is specified in the new HS parameter SCHDEFHR.

Tasks are coloured based on the SLA dates of the associated issues: tasks that breach the SLA are coloured red; tasks within the target SLA are green; tasks on the target SLA date are orange.

Completed Task in Breach of SLA

The following icons may be shown on scheduled tasks:

Icon

Meaning

The task is complete.

The task has been allocated to more than one operative.

A task scheduling note has been entered.

Special conditions exist for the plot.

Indicates this is where the operative currently is (only if using mCare).

The task is double-booked (that is, the start time for the task occurs before the end of another task assigned to the same operative). This is only shown on multi-day views.

Rescheduling a Task

You can reschedule a scheduled task by:

  • Dragging it to a different operative and/or time on the calendar.

  • Double-clicking the task (or using the context menu) to bring up the Update Task dialogue box and updating the date, time and/or duration.

  • Making a task the first task of the day. Right-click the task and choose Set As First Task from the context menu. This moves the selected task to the start of the operative‘s working day, then reschedules the other tasks to follow it.

In Single Day view, you can change a task’s duration by dragging the left or right side of the task.

Unscheduling a Task

You can unschedule a task by right-clicking it to display the context menu, choosing Unschedule and clicking Yes. This removes the date and time from the task, but it remains assigned to the operative.


Task Context Menu

Right-clicking on a task in the calendar brings up a menu that allows you to do various things with the task.

  • Update Date/Time

  • Unschedule

  • Joint Task

  • Add Schedule Note

  • Schedule Additional Task

  • Set as First Task

  • Update Task Description

  • To be Confirmed

  • Confirmed

Creating a Joint Task

If you want to schedule more than one operative for a task, create a joint task. Right-click the scheduled task and choose Joint Task. This allows you to add up to three other operatives who will jointly work on the task.

Open

Adding a Schedule Note

If you want to add a scheduling note to a scheduled task, right-click the task in the calendar and choose Add Schedule Note. This prompts for a free-text note.

Open

A flag icon on the task indicates that a scheduling note has been added.

To update a schedule note, click the flag icon; this opens a browse of scheduling notes for the task, in a popup window.

Creating a New Task

Tasks should only span one day. If a task will run over more than one day, schedule a new task based on the existing scheduled task.

Right-click the task and choose Schedule Additional Task. This provides the following sub-menu options:

  • Today

  • Next Day

  • Next 7 Days - This has further sub-options that list the next seven days.

  • Select - This allows you to choose a specific date using a date picker.

You will be prompted to confirm that you want to create a task on the date you specify.

This creates a new task with the same duration, and at the same time of day.


Customer Care Travel Times

To improve the accuracy of scheduling tasks in Customer Care, you can allow travel times to be built into the schedule. This allows for more accurate appointment times and improved customer satisfaction.

If the HS parameter CCTRTIME is set to Y:

  • In multiple day view:

    • When dragging an unscheduled task onto the calendar, the calculated start time includes the travel time to get from the previous task to the selected task. Note if the previous task is on the same development then no travel time will be allocated as it’s assumed the travel time would be so short as to not be significant.

    • The duration shown in the bottom right of the task cell also shows the travel time. For example, if a task has a duration of 2 hours and travel time of 30 minutes the duration would show as 0.5 / 2h.

    • The tooltip shows the travel time to get to the task below the appointment date/time row.

    • Open
  • In single day view

    • When first dragging an unscheduled task onto the single day view, if the selected start time including the calculated travel time to get there is before the end of the previous task, the start time of the task is adjusted to allow sufficient travel time.

    • For subsequent updates to the task, a warning is given if the task date or time is amended and there is insufficient travel time between the task and the previous task.

    • The day view shows a virtual task that represents the travel time. This is read-only and coloured blue to distinguish it from activity workbench entries.

      Open

      For mCare operatives a van icon is shown in the top right of the travel time task if the operative is currently travelling to the next task.

Other processes that update task times also take travel time into account.

📌Note: Travel time is not calculated for the operative's first appointment of the day.

Reschedule Remaining

This is an action on the task context menu. For a selected task, the remaining tasks for the operative and day will be re-calculated based on the end time of the selected task. This also re-evaluates the travel time based on the end times for each subsequent task.

This option is available regardless of the setting of the HS parameter CCTRTIME.

Travel Time Configuration

Coins ERP+ uses the ‘Distance Matrix API’ provided as part of the Google Maps API service to calculate the travel time. To use this API, you will need a Google Maps API key. You can obtain this from Google. Enter this key in the system parameter GMAPLKEY to enable the service.

You can choose whether the travel time calculation takes account of traffic: set the HS parameter CCTRMODE to pessimistic, optimistic or best-guess, depending on which traffic model you want to use.

Because the travel times are calculated to the minute, you can round up the appointment time to the next 5, 10, 15 or 30. Set the HS parameter CCAROUND to the rounding interval you want to use This applies to all places where the appointment time is calculated using the travel time.


Skill Sets

Skill sets for Customer Care tasks and operatives allow you to ensure that an operative with the appropriate skills is assigned to the task.

Maintaining Skill Sets

Skill Set Maintenance is a new function that allows you to define the master list of skill sets for the company.

Open

Specifying Operativesʼ Skills

When maintaining a sales staff record, you can now select the skills that the operative has.

If the HS parameter SKILLSET is set to Y, a Skill Sets selection list is available, in which you can select one or more skills.

Open

Skills Required for a Task

When updating a task, you can now select the specific skills that are required to complete it.

If the HS parameter SKILLSET is set to Y, a Required Skill Sets selection list is available, in which you can select one or more skills.

Open

When you save a task, if an internal staff operative has been assigned, Coins ERP+ checks that the selected operative has the required skill sets for the task. If not, a warning is displayed.

Open

Scheduling a Task

If the HS parameter SKILLSET is set to Y, operativesʼ skills and the required skills for tasks are now shown on the scheduler.

  • In the unscheduled task list, the first row of each task shows the short code of the skill sets required to complete the task. The tooltip shows the full description of the skill sets required for the task.

  • In the operatives list in the calendar section, the fourth row of the operative details shows the short codes of the operative skill sets. The tooltip shows the full description of their skill sets.

  • The tooltip for a scheduled task also shows the required skill sets.

In the scheduler filter, you can now select a single skill set. This then shows any unscheduled tasks that require that skill set, and any operatives with the selected skill set.

Open

When you drop an unscheduled task onto the calendar, Coins ERP+ checks that the selected operative has the required skill sets for the task. If not, a warning is displayed.


Regenerate Schedule

To ensure adequate performance of the schedule a new set of day summary records will be created for each action. The existing Regenerate Schedule option has been enhanced to create these for existing tasks and actions. This will need to be run if users want to see existing actions/tasks in the Scheduler.

Open